- Formal submission of the architects’ tentative sketch plan to the township of Bala Cynwyd (April, 2010)
- Scheduled Historical Commission and Township Planning Commission review meetings review meetings (May or June, 2010)
- Sketch plan approval; and then estimation of development time frames (August, Fall, 2010)
- Engineering, permitting; submittals Township, County, State. (Late 2010, most if not all of 2011)
- Preliminary Plan approval by Township (Estimated between 2nd half 2011, and Spring, 2012; 12 to 18 months after sketch plan approval)
- Engineering, permitting; submittals Township, County, state. (Late 2010, most if not all of 2011)
- Development/construction estimated to begin by 2nd half of 2012.